Palestina, Update 5

The engineers of Membrane Systems Europe, Adverio and the local Palestinian contractor have placed the double membrane roofs and finalized the mechanical commissioning this week 8 (2016). The reactors are from this moment on gas tight. To start the biological process manure is pumped in the tanks this will take several weeks. In the mean the transformer and the CHP unit will be connected by the network company. Hereafter the CHP unit will start producing electricity and heat. 

The facility is designed to process 50 ton/day of cattle manure and organic waste, 365 days a year. The AD facility will provide electricity to local communities through the grid and directly to the neighbouring cattle farm.