YNS (Ukraine), Update 1

Adverio has started with the first phase of engineering works for a 3 MW CHP Biogas Facility in Ukraine, for our client UTC.

Our project manager in Ukraine visits the construction site every week for consultation with the contractor. The tanks are welded on site the weather conditions are not stopping the construction.

The main objective is to produce electricity from sugar beet pulp. This results in a greenhouse gas emissions reduction and a more sustainable sugar production process.